The Brightwood-Lincoln Elementary School Prequalification Committee, acting in accordance with Chapter 193 of the Acts of 2004, an Act Further Regulating Public Construction in the Commonwealth, has evaluated all responses to the Statement of Qualifications. A notice has been sent to the following prequalified trade bidders. Only these specific trade bidders shall be permitted to submit a bid for their respective trade on the proposed Project.

Prequalified Trade Bidders:

Miscellaneous Metals:
Avid Iron Works, Inc.
North Shore Steel Co. Inc.
SMJ Metal Co., Inc.
United Steel Inc.

Plumbing:
Adams Plumbing & Heating, Inc.
B-G Mechanical Contractors, Inc.
Grassechi Plumbing & Heating, Inc.
Harry Grodsky & Co., Inc.
Harold Brothers
TJ Conway & Co.
William F. Lynch Co., Inc.

Tile:
Ayotte & King For Tile, Inc.
Capital Carpet & Flooring Specialists, Inc.
Joseph Cohn & Sons Tile & Terrazzo, LLC
M. Frank Higgins & Co., Inc.

Painting:
Dandis Contracting Inc.
Grimaldi Painting Inc.
John W. Egan Co., Inc.
King Painting, Inc.
O’Byrne Painting & Contracting, Inc.

Accoustical Tile:
Central Ceilings, Inc.
Conn Accoustics, Inc.
H. Carr & Sons, Inc.


Electrical:
Collins Electric Co., Inc.
M.L. Schmitt Inc.
Universal Electric Co., Inc.
Wayne J. Griffin Electric, Inc.

Fire Protection:
Carlysle Engineering, Inc.
Cogswell Sprinkler Co., Inc.
SRI Fire Sprinkler, LLC
Wolverine Fire Protection Co.
Yankee Sprinkler Co.

Glass & Glazing:
A&A Window Products, Inc.
Chandler Architectural Products, Inc.
Greenfield Glass Company
Kapiloff’s Glass Inc.
R&R Window Contractor’s, Inc.

HVAC:
Adams Plumbing & Heating, Inc.
B-G Mechanical Contractors, Inc.
General Mechanical Contractors, Inc.
Harry Grodsky & Co., Inc.
Harold Brothers
Kleeberg Mechanical Services, LLC.
N.B. Kenney Co., Inc.
TJ Conway & Co.
William F. Lynch Co., Inc.

Masonry:
C&S Co., Inc.
Champlain Masonry
Fernandes Masonry
Lighthouse Masonry, Inc.
Marmello Bros. Construction
Sullivan & Narey Construction Co., Inc.

Metal Windows:
A&A Window Products, Inc.
Lockheed Window Corp.
R&R Window Contractor’s, Inc.

Resilient Flooring:
Ayotte & King For Tile, Inc.
Capital Carpet & Flooring Specialists, Inc.
M. Frank Higgins & Co., Inc.

Roofing & Flashing:
Capeway Roofing Systems, Inc.
Gibson Roofing Inc.
Greenwood Industries, Inc.
J.D. Rivet & Co., Inc.
Rockwell Roofing, Inc.
Silktown Roofing, Inc.
Stanley Roofing Co., Inc.
Titan Roofing, Inc.

Waterproofing:
Armani Restoration
Chapman Waterproofing Company
East Coast Air Barrier & Restoration, Inc.
PJ Spillane Co., Inc.
Superior Caulking & Waterproofing Co., Inc.

Elevators:
Bay State Elevator Company
Delta-Beckwith Elevator Company







Sincerely,


Theo G. Theocles, Esq.
Deputy Procurement Officer
City Hall, Room 307
City of Springfield
36 Court Street
Springfield, MA 01103

The City of Springfield supports the goal of twenty percent minority and women participation in all contracts. No questions will be answered unless received by the Chief Procurement Officer at least 7 days prior to the expiration of the time set for submitting bids or proposals. The Chief Procurement Officer reserves the right to waive any informality in and to reject any or all bids if it is in the public interest to do so.


Available Solicitations

As of 12:04 am Tuesday, April 16, 2024

24-222 - For Sale: Redevelopment Boston & Albany Railroad at Factory Road/Hendee Street
End date: Monday May 13, 2024 at 2 p.m.

24-221 - Mary O. Pottenger School Parking Lot Improvement Project
End date: Thursday May 2, 2024 at 2 p.m.

24-220 - Frank H Freedman School Parking Lot Improvement Project
End date: Thursday May 2, 2024 at 2 p.m.

24-219 - Daniel B. Brunton School Parking Lot Improvement Project
End date: Thursday May 2, 2024 at 2 p.m.

24-180 - Roadway & Sidewalk Improvements - Arterial and Residential Streets including Sidewalks
End date: Wednesday May 1, 2024 at 2 p.m.

24-205 - Request for Proposals for Springfield's 2024 Public Mural Program
End date: Monday April 29, 2024 at 2 p.m.

24-226 - Flooring Installation at Mary O. Pottenger Elementary School
End date: Friday April 26, 2024 at 2 p.m.

24-225 - Abatement at Mary O. Pottenger Elementary School
End date: Thursday April 25, 2024 at 2 p.m.

24-224 - Abatement at Samuel Bowles Elementary School
End date: Thursday April 25, 2024 at 2 p.m.

24-223 - Abatement at Springfield Public Day Middle School
End date: Thursday April 25, 2024 at 2 p.m.

24-203 - RFP: Review and Update of Historical District Guidelines, Policies and Procedures
End date: Wednesday April 24, 2024 at 2 p.m.

24-213 - Purchase of Bituminous Concrete
End date: Tuesday April 23, 2024 at 2 p.m.

24-217 - On-Call Generator Maintenance, Repairs, and Testing
End date: Friday April 19, 2024 at 2 p.m.

24-182 - 2024 Sidewalk Program - Safe Streets and Roads for All
End date: Thursday April 18, 2024 at 2 p.m.

24-216 - Renovation of Hubbard Park Tennis Courts
End date: Thursday April 18, 2024 at 2 p.m.

24-196 - Price Agreement: Scott Air-Pak Parts and Services
End date: Thursday April 18, 2024 at 2 p.m.

24-214 - PA: Medical Supplies for the Springfield Public Schools Nursing Programs
End date: Wednesday April 17, 2024 at 2 p.m.

24-215 - For Sale: Eight (8) Obsolete/Surplus Fire Department Vehicles
End date: Wednesday April 17, 2024 at 2 p.m.

24-210 - Central High School Auditorium & Gym Bleacher Renovation Project (Rebid)
End date: Wednesday April 17, 2024 at 2 p.m.