RFQ Phase I

Downloadable Documents

 Click here to download the Phase I RFQ

(current as of 9/21/2012 at 3:50PM)

RFQ Questions and Answers Update - October 9th, 2012 - Question 16:

The RFP/Q downloaded from the website indicates that responses are due at 2:00 P.M. on October 11, 2012. However, on another portion of the website, it is stated that "The Phase 1 proposals are due by Oct. 10 at 5 p.m." What is the deadline?

Answer: The deadline is October 11, 2012 at 2:00 P.M.  However, the City will not reject a proposal as non-compliant as to time of submission if it is received by 5:00 P.M. on October 11, 2012.

 

RFQ Questions and Answers - October 2nd, 2012

Questions/Responses pursuant to Section 4.D. of the Phase I - RFP/Q

 

RFQ Update - October 2nd, 2012

Important Notice: Permitted Contacts

Effective October 11th, 2012: The City recognizes that proposers need access to the same types of information that would be required by any party considering a major development in the City.  Accordingly, after October 11, 2012, the date by which the Phase I-RFQ/P responses are due, the proposers may contact City employees at the various City departments to obtain information customarily needed by a developer interested in developing a building site within the City.  For example, this would include information concerning zoning, permits, building codes and restrictions, sewer, water, electricity, police, fire, and traffic.  Contacts with the Mayor, the Mayor?s office, the Chief Development Officer, and members of the City Council are still prohibited.  The Phase II-RFQ/P may contain other information concerning permitted contacts by proposers with City employees