2007 Sidewalk Construction Project

MUNICIPAL INFRASTRUCTURE

Project Manager: Al Chwalek, DPW
Project Location: Various Locations throughout the City
Engineer: Department of Public Works
Contractor:
Gomes Construction
Project Budget:
$1.6 million
Anticipated Start Date:
Underway
Anticipated Completion Date:
July 2009

Description:
The sidewalk construction was comprised of 2 parts.

  • As a result of school redistricting, five (5) miles of sidewalk will be constructed at an approximate cost of $1,200,000.
  • Replacement of existing sidewalks through the sidewalk application process. Residents apply through the DPW to have existing public sidewalk replacement. Approximate cost: $400,000.

Project Status as of June 1, 2009:

The school sidewalk construction component is complete. Bradley Road, Plumtree Road, Parker Street, Grayson Drive, and Oak Street (Indian Orchard).

The residential sidewalk replacement program is 99% complete ith only minor work remaining.  


More Project Updates:








Page last updated:  Wednesday, June 03, 2009 04:27 pm